Progress Update on Housing Asset Management, Investment Programme and Compliance

08/07/2019 - Housing Asset Investment Programme

The report provided the committee with a progress update on matters in relation to the following:

·         Axis Contract

·         Stock condition survey

·         Planned Maintenance programme

·         Compliance

·         Keystone

·         Snakes Hill

 

The update report followed on from the previous progress report on these matters which were provided to the 5th March 2019 Community, Health & Housing Committee.

 

A presentation was given by Steve Summers. 

 

The Chair requested an update for Snakes Hill and the stages of procurement for the next committee.    

 

A motion was MOVED by Cllr Hossack and SECONDED by Cllr Kerslake to agree the recommendations.

 

A vote was taken by a show of hands and it was RESOLVED UNANIMOUSLY:

To note the contents of the report. 

 

Reasons for Recommendation

The report highlights progress on Asset Management, Capital Programme and Compliance in Housing. Members were invited to comment on the report contents.