Skip to main content

Agenda item

19/01371/FUL - 65 Magnolia Way, Pilgrims Hatch, Brentwood, Essex. CM15 9PP

Minutes:

Planning permission is sought for the construction of a two storey side extension and single storey front and rear extension with roof lantern. The original submission proposed extensions which were in alignment with the ridge line and front and rear building lines. In order to address neighbour concerns, a revised proposal (Drawing numbers:  Site Location Plan (rev A) and  REVO/4181 revC) has been submitted which illustrates a reduction in height and is setback from the front elevation.

 

Daryl Cook presented this report.

 

Ms Jill Brisley on behalf of the residents addressed the committee in objection of the application.

 

Cllr Davies spoke as Ward Councillor raising concerns in respect of the double aspect as a cause of concern for surrounding residents.

 

Following a full discussion Cllr Nolan MOVED and Cllr McCheyne SECONDED that the application be approved.

 

A recorded vote was taken and Members voted as follows:

 

FOR:  Cllrs Nolan, McCheyne, Tierney, Tanner, Jakobsson, Fryd, Keeble and Barratt

 

AGAINST: Cllr Chilvers

 

ABSTAIN: Cllrs Mynott and Haigh

 

It was RESOLVED that the application be APPROVED subject to the following conditions:

 

1 TIM01 Standard Time - Full

The development hereby permitted shall be begun before the expiration of three years from the date of this permission.

 

Reason: To comply with Section 91 of the Town and Country Planning Act 1990, as amended by Section 51 of the Planning and Compulsory Purchase Act 2004.

 

2 DRA01A Development in accordance with drawings

The development hereby permitted shall not be carried out except in complete

accordance with the approved drawing(s) listed above and specifications.

 

Reason: To ensure that the development is as permitted by the local planning

authority and for the avoidance of doubt.

 

3 MAT03 Materials to match

The materials to be used in the construction of the external surfaces of the building hereby permitted shall match those used in the existing building.

 

Reason: In order to safeguard the character and appearance of the area.

 

4 CON1 Construction Method Statement

No development shall take place, including any works of demolition, until a

Construction Method Statement has been submitted to, and approved in writing by, the local planning authority. The approved Statement shall be adhered to throughout the construction period. The Statement shall provide for:

i. the parking of vehicles of site operatives and visitors

ii. loading and unloading of plant and materials

iii. storage of plant and materials used in constructing the development

iv. the erection and maintenance of security hoarding including decorative displays

and facilities for public viewing, where appropriate

v. wheel washing facilities

vi. measures to control the emission of dust and dirt during construction

vii.a scheme for recycling/disposing of waste resulting from demolition and

construction works

viii. hours of working and hours during which deliveries may be taken at the

site

 

Reason: In the interests of highway safety, visual and neighbour amenity.

 

 

Reasons for approval

 

The proposal accords with the relevant policies of the

development plan as set out in the report. The Council has had regard to the concerns expressed by residents but the matters raised are not sufficient to justify the refusal of permission.

 

 

 

 

 

Supporting documents: