179.

Apologies for Absence

Additional documents:

Minutes:

There were no apologies were received, all committee members were present.

 

180.

Minutes of the Previous Meeting pdf icon PDF 117 KB

Additional documents:

Minutes:

The minutes from the previous Community, Health and Housing Committee held on 18th September 2017 were approved as a true record.

 

181.

Verbal update

Additional documents:

Minutes:

Housing KPI’s

Mrs Marsh gave an update to the members on the Housing KPI’s.

 

Garage Site Re-Development

 

Mr Morris presented an update to members on garage site re-development. The first phase at Magdalen Terrace has been completed and the three new build family houses were tenanted successfully.

 

The second phase at Knight’s Square has achieved build completion and the four single-storey properties are due to be tenanted imminently.

 

The third phase at Whittington Road has been consulted upon and submission of relevant planning applications by the architects will be completed shortly.

 

182.

Variation of the agenda

Additional documents:

Minutes:

The Chair moved that item 14 – Courage Playing Fields be debated before item 4.

 

A vote was taken by a show of hands and it was RESOLVED UNANIMOUSLY.

 

 

183.

Fees & Charges pdf icon PDF 76 KB

Additional documents:

Minutes:

Fees and charges made by the Council for various services were reviewed on an annual basis by the relevant Committees relating to the services provided.

 

Recommended amendments to the fees and charges were incorporated into the budget setting process to take effect from the following financial year.

 

A motion was MOVED by Cllr Hossack and SECONDED by Cllr Poppy to approve the recommendation in the report.

 

Officers explained any variation in proposed Fee and Charges to Members.

 

A vote was taken by a show of hands and it was RESOLVED that:

 

1.    That Members agree to the proposed charges for 2018/19 as attached in Appendix A, B, and C subject to the budget setting process.

 

Reason for recommendation

Officers reviewed the fees and charges annually and this would be used to inform the 2018/19 budget setting process.

 

(Cllr Ms Rowlands declared a pecuniary interest under the Council’s Code of Conduct by virtue private landlord (HMO) and therefore didn’t take part in the debate or vote).

 

184.

Courage Playing Fields pdf icon PDF 86 KB

To follow.

Additional documents:

Minutes:

The report considered a possible option in the development of an alternative cricket pitch site in Courage’s Playing Fields. It recommends the further scoping of using soil relocation as a means of facilitating the development of an alternative viable cricket pitch within the whole site.

 

The Chair, informed the Committee of the advice received by the Health and Safety Officer to the viability of the second field used by Shenfield Cricket Club.  The Chair had meet with members of Shenfield Cricket Club and discussed their need for the Cricket Club to play on two pitches and expressed their concerns on the limitation with the current location of the second pitch.  A Health and Safety audit was undertaken and it was agreed that action was required before the start of the 2018 cricket season with nets needing to be installed to meet the Health and Safety requirements. However, it was felt that an alternative site for a second cricket pitch might provide a better long-term solution for the club and as such a review for the relocation of the second field would be investigated.

 

A presentation to Members was given by Mrs Anderson.

 

Cllr Rowlands, Ward Member.  Expressed that the relocation will be a good opportunity for Shenfield Cricket Club and asked that a full consultation is undertaken with residents.

 

Cllr Cloke, informed the Committee that a parking review around the site is currently under review.

 

A full traffic assessment will need to be undertaken before any Planning Permission submitted.         

 

Cllr Clarke, asked about the possibility of Shenfield Cricket Club’s second field being at different venue.  If the project is not viable, this may be an option.                                                                                                                  

 

A motion was MOVED by Cllr Hossack and SECONDED by Cllr Poppy to approve the recommendation in the report. 

 

A vote was taken by a show of hands and it was RESOLVED UNANIMOUSLY:

 

1.    That officers scope the viability of using soil relocation to provide a second alternative cricket pitch location in Courage’s Playing Fields.

 

Reasons for Recommendation

Comments received from Sport England as part of the Local Development Plan consultation, stated that a Leisure Strategy is required that assesses Council owned sports and leisure facilities in order that the Council can continue to work with partners to ensure that appropriate provision is made for the residents of Brentwood. The strategy should not only consider how the Council can provide services, but also how other partners can. The strategy should also use current sports facility evidence to identify strategic priorities to then inform what will be included in the Council’s Infrastructure Delivery Plan. Following this feasibility work, the Council will then be able to determine which projects will be funded by the Community Infrastructure Levy (CIL) and those funded by planning obligations.

 

The Council’s Asset Management Strategy 2014/15 also sets out the need to

obtain maximise income where possible from its asset portfolio.

 

185.

Re-procurement repairs and maintenance contract pdf icon PDF 82 KB

Additional documents:

Minutes:

In 2014, Brentwood Borough Council entered into two contracts with Oakray and Wates to carry out repairs to Housing Stock. These contracts were due to expire in 2019.

 

Brentwood Borough Council wished to enter into one contract through a re-procurement exercise.

 

A presentation to Members was given by James Henderson, Basildon Borough Council and Peter Gudge, Echelon Consultancy.

 

The Chair asked for members to join a cross party working group.

 

The Members of the working group together with the Chair will be:- Cllr Clarke (LD), Cllr Mrs Hubbard (IND), Cllr Willes (CON), Cllr Poppy (CON), Cllr Cloke (CON) and a Member of the Labour Group, which is to be confirmed.

 

A motion was MOVED by Cllr Hossack and SECONDED by Cllr Poppy to approve the recommendations in the report.

 

A vote was taken by a show of hands and it was RESOLVED UNANIMOUSLY that:

 

1.    That the Committee note that Housing Services will be entering into a re-procurement exercise in relation to repairs and maintenance contracts.

 

2.    That the Committee agree to cross party working groups throughout the procurement process.

 

3.    That Committee does now agree the members that are to be included in the working group.

 

4.    That a full schedule of working group dates are published in advance to members of the Working Group and that consideration is given to timings suitable for member attendance.

 

Reasons for Recommendation

As a responsible landlord it was important that the Council demonstrates that it had vigorously explored and pursued the best services for our customers.

 

The current contracts presented many issues for the management and other

more cost-effective options were available by re-procuring into one contract.

 

 

 

186.

Events on Open Spaces - Fees & Charges/ Procedure/Protocol pdf icon PDF 105 KB

Additional documents:

Minutes:

To update existing Terms and Conditions for Events on Open Spaces to ensure up to date procedures/legislation.

 

To introduce some new categories on the fee and charges (Appendix A of the report).

 

Recommended amendments to fees and charges in respect of events on open spaces for commercial and community events were incorporated into the budget setting process to take effect from the following financial year.

 

A motion was MOVED by Cllr Hossack and SECONDED by Cllr Poppy to approve the recommendation in the report.

 

A vote was taken by a show of hands and it was RESOLVED UNANIMOUSLY that:

 

1.    Members to agree the new categories on fees and charges schedule (Appendix A of the report).

 

2.    Members to agree the introduction of the on-line application form

(Appendix C of the report) and payment form for requests for events on open spaces from 1st April 2018.

 

3.    Members to agree the amendments in Terms & Conditions (Appendix B of the report), with immediate effect.

 

Reasons for Recommendation

Including new categories on the fees and charges would clarify areas that have not been included previously to help make the procedure more comprehensive and clear.

 

Introducing on-line payment form for applicants (from 1st April 2018) to use rather than invoicing them will ensure payment is received prior to event – the applicants would only be given the link to this on-line form once the event has been given approval.

 

From 1st April 2018 the on-line application form with have mandatory categories (i.e. attaching relevant paperwork such as risk assessments, site plans, insurance policies, at the point of applying), this would be in keeping with a modern Council and providing an efficient and effective system.

 

Ensuring that the Terms and Conditions (Appendix B) and the Application Form (Appendix C) were up to date with procedures and legislation.

 

For safety reasons on Council owned land the Council would not permit any firework displays apart from professional organised displays whereby the organisers are members of the British Pyrotechnics Association and adhere to BPA professional industry standards.

 

New categories as detailed in section 4 were introduced for further clarity things after listening to feedback from applicant’s that did not previously fit into any of the existing categories. The discount for multiple events for large events would help the organiser’s plan events in advance to secure the discount. To receive the discount the applicant would need to pay in advance.

 

(Cllr Cloke and Cllr Wiles declared a non-pecuniary interest under the Council’s Code of Conduct by virtue of being a member of the Starburst Firework Display Team).

 

187.

Rent Setting 2018/2019 pdf icon PDF 102 KB

Additional documents:

Minutes:

The report sought the recommendations of the Community, Health and Housing Committee on the proposed rent levels for 2018/19.

 

The recommendations would be considered by the Policy, Projects and Resources Committee when the final recommendation would be made as part of the budget setting process. The final decision will be made by Ordinary Council on the 28th February 2018.

 

A motion was MOVED by Cllr Hossack and SECONDED by Cllr Poppy to approve the recommendations in the report.

 

A vote was taken by a show of hands and it was RESOLVED that:

 

1.    To decrease Rent by 1% from April 2018 and for the next year.

 

2.    That Shared Ownership rent be increased by CPI + 1%.

 

3.    To increase General Fund Property Rents by 3%.

 

4.    To apply a 3% increase to Garage Rents.

 

5.    To note that Service charges to be brought in line with actual costs and the final charging proposals to be brought to Policy, Projects and Resources Committee to inform the 2018/19 charging levels as part of the budget setting process.

 

6. To apply the formula rent to all new tenancies from April 2018/19.

 

7.    To note that rents to be charged at CPI + 1% from 2020/21.

 

Reasons for Recommendation

The recommendations were to follow the guideline 1% decrease 2018/19 and the following year as this is what has been set by government.

 

The following assumptions have been taken into account when considering the Rent Setting for 2018:

 

·         The financial viability of the HRA business plan

·         Provision for a repairs capital programme

·         Development funding for new homes

·         No allowance has been made for growth bids

·         Affordability for tenants

 

(Cllr Ms Rowlands declared a pecuniary interest under the Council’s Code of Conduct by virtue that her partner has a freehold property that is a shared ownership with the authority, therefore Cllr Rowlands did not take part in the debate or vote.  Cllr Wiles declared a declared a pecuniary interest under the Council’s Code of Conduct by virtue that his wife is a tenant of the authority, therefore Cllr Wiles did not take part in the debate or vote). 

 

188.

Housing Audit pdf icon PDF 85 KB

To follow.

Additional documents:

Minutes:

The report was to inform the Community, Health & Housing Committee of the

outcome of the 2016/17 and 2017/18. Audit review for Housing Services as part of the Council’s approved Audit plans for 2016/17.

 

The outcome of the 2016/17 internal audit review was reported to the Audit Committee on the 27th September 2017. As set out within that audit report Officers provided responses to the recommendations and are currently developing an action plan with appropriate priorities and timescales. The

action plan will be reported to a future meeting of this committee for monitoring.

 

The outcome of the 2017/18 internal audit review is due to be reported to the Audit Committee on the 17th January 2018. Officers are currently drafting management responses to this audit report. As above officers will develop an action plan which will be reported to a future meetings of this council for monitoring.

 

A motion was MOVED by Cllr Hossack and SECONDED by Cllr Poppy to approve the recommendations in the report.

 

Cllr Ms Sanders left the room during the debate, and therefore was unable to vote.

 

A vote was taken by a show of hands and it was RESOLVED.

 

1.    That the Committee receives and notes the contents of Audit report as attached at Appendix A.

 

2.    That the Committee agree that a further report on progress made on implementing the recommendations is presented to the next Committee.

 

Reasons for Recommendation

To monitor the progress of work against the highlighted actions recommended arising from the Audit Report and management actions in response to those recommendations.

 

189.

Empty Homes Stats/KPI's Action pdf icon PDF 98 KB

Additional documents:

Minutes:

At the meeting of the Community, Health and Housing Committee on 18thSeptember 2017 the draft Empty Homes Strategy was adopted by Members.

 

Officers were instructed to report back to subsequent meetings to provide information on progress and performance indicators regarding empty homes.

 

Mr Carter made a presentation to Members on Empty Homes KPI’s.

 

A motion was MOVED by Cllr Hossack and SECONDED by Cllr Poppy to approve the recommendations in the report, subject to two additional recommendations to state:-

 

2.4.  That Brentwood Borough Council instigates dialogue with Essex    Housing Officers Group (Environmental) to adopt a Empty Homes Task Force for Essex.

 

2.5  That Brentwood Borough Council investigates the possibility of increasing the Empty Homes premium to an additional 100% over standard Council Tax as mentioned in the Government Budget, this is subject to approval of the Policy, Project and Resource Committee.

 

A vote was taken by a show of hands and it was RESOLVED UNANIMOUSLY that: 

 

1.    Members note the contents of the report and actions taken to deal

with empty homes.

 

2.    Members instruct officers to prioritise properties for action to

concentrate efforts on identified locations.

 

3.    Officers are instructed to verify data provided to inform Government Empty Home statistics and to liaise with Basildon DC Billing & Benefits Team.

 

4. That Brentwood Borough Council instigates dialogue with Essex    Housing Officers Group (Environmental) to adopt a Empty Homes Task Force for Essex.

 

5.That Brentwood Borough Council investigate the possibility of  increasing  the Empty Homes premium to an addition 100% over standard Council Tax as mentioned in the Government Budget, this is subject to approval of the Policy, Project and Resource Committee.

 

 

Reasons for Recommendation

To ensure that effective action was taken to reduce the number of empty homes in the Borough within existing resources where possible.

 

190.

Housing Garage Sites - Modular Housing pdf icon PDF 109 KB

Additional documents:

Minutes:

At the 18th October 2017 Ordinary Council, the following Motion was moved by Cllr Hossack, seconded by Cllr Poppy and was carried unanimously.

 

That this Council investigates the opportunity that the use of modular construction homes, in conjunction with the utilisation of our multiple garage site assets, could present in addressing the need to meet our housing supply needs quickly and efficiently whilst at the same time addressing the need for affordability.

 

That the council also considers as part of this project, the opportunity for social return by of having a local assembly plant within the Borough that would provide the opportunity for employment, skills and apprenticeships and the support of local supply businesses whilst at the same time, meeting the housing need at source.’

 

The report set out the initial issues and options regarding the future provision of the housing garage sites.

 

Members support the idea and would like to maybe visit provider and see a presentation in the future.

 

A motion was MOVED by Cllr Hossack and SECONDED by Cllr Poppy to approve the recommendation in the report.

 

A vote was taken by a show of hands and it was RESOLVED UNANIMOUSLY that:

 

1.    That the Committee authorises Officers to investigate in more detail the following:

 

i.          Options in relation to the development of the Council’s Housing Garage sites including modular housing.

ii.         Options in relation to developing a local assembly plant within the Borough to provide modular housing.

 

2.    That a further report on the options as set out above is provided to the next Community, Health & Housing Committee.

 

Reasons for Recommendation

To enable BBC to maintain its responsibilities and fulfil its obligations as a landlord.

 

A review of all the Council’s garage sites would be required to ensure asset

management decisions were based on sound information.

 

It was vital that the Council had up to date information about condition of the

HRA stock in order to support its investment decisions each year. The risks in not having this information include the failure to provide adequate resources to tackle repairs and maintenance that subsequently led to the need for replacement at a much higher cost.

 

191.

Health and Wellbeing Strategy 2017-2022 pdf icon PDF 87 KB

Additional documents:

Minutes:

 

The report was to update members on the revised Health and Wellbeing Strategy for Brentwood for 2017- 2022 (Appendix A).

A presentation to Members was given by Mrs Hanlon.

 

A motion was MOVED by Cllr Ms Sanders and SECONDED by Cllr Mrs Davies to approve the recommendation in the report.

 

A vote was taken by a show of hands and it was RESOLVED UNANIMOUSLY that:

 

1.    The Health and Wellbeing Strategy 2017-2022 (Appendix A) for Brentwood be adopted.

 

Reasons for Recommendation

The previous strategy had expired and needed to be amended in light of the new board priorities.

 

192.

Termination of Meeting

Additional documents:

Minutes:

At 9.00pm in accordance with Rule 10.1 of the Council’s procedural rules, Members resolved to continue the meeting for a further 30 minutes

193.

Leisure Strategy pdf icon PDF 96 KB

Additional documents:

Minutes:

193.      Leisure Strategy

 

It was agreed by Members at the Council’s Policy, Projects and Resources Committee in June 2017 that the Leisure Strategy work would be split into three phases. Phase 1 would include King George’s Playing Fields and  Warley Playing Fields. Phase 2 would include the Council’s Play Areas and phase 3 would include the Brentwood Centre and the longer term strategic view of the Council’s Leisure facilities. It was also agreed that the Leisure Strategy Working Group would scrutinize the Leisure Strategy work and put forward any key findings and recommendations to the Corporate Projects Scrutiny Committee. At the 21 November 2017, Corporate Projects Scrutiny Committee, the following recommendations were agreed by the Committee, and are in front of this committee for their consideration (subject to the Council’s calling in period).

 

A motion was MOVED by Cllr Hossack and SECONDED by Cllr Poppy to approve the recommendations in the report, subject to an additional recommendation 2.2 to state:-

 

2.2   That the Community, Health and Housing Committee agrees to replace the phased approach to the Leisure Strategy with workstreams going forward to enable greater flexibility.

 

A vote was taken by a show of hands and it was RESOLVED that:

 

1.    That officers Members note the report and agree the recommendations from the Corporate Projects Scrutiny Committee on 21 November 2017 which are set out as follows:

 

a)    Officers facilitate a workshop with industry experts and members to drive the outcomes and principles of the Council’s Leisure Strategy.

 

b)   Following on from the workshop session, it is recommended that officers liaise with industry experts to develop the Leisure Strategy for Brentwood to enable the Council to deliver the outcomes, agree the short-term priorities and longer-term objectives.

 

c) That the officer and members explore the potential of commencing a procurement process in parallel with the development of the leisure strategy.

 

2.        That the Community, Health and Housing Committee agrees to replace the phased approach with workstreams going forward to enable greater flexibility.

 

Reasons for Recommendation

As part of the Council’s due diligence in delivering a successful Leisure Strategy, Members and officers need to have a complete picture of the current associated costs, risk profiles of the Borough’s Leisure facilities and identify opportunities for income generation.

 

Comments received from Sport England as part of the Local Development Plan consultation, stated that a Leisure Strategy is required that assesses Council owned sports and leisure facilities in order that the Council can continue to work with partners to ensure that appropriate provision is made for the residents of Brentwood. The strategy should not only consider how the Council can provide services, but also how other partners can. The strategy should also use current sports facility evidence to identify strategic priorities to then inform what will be included in the Council’s Infrastructure Delivery Plan.

 

Following this feasibility work, the Council will then be able to determine which projects will be funded by the Community Infrastructure Levy (CIL) and those funded by planning obligations.

 

The Council’s  ...  view the full minutes text for item 193.

194.

Termination of Meeting

Additional documents:

Minutes:

At 9.30pm in accordance with Rule 10.1 of the Council’s procedural rules, Members resolved to continue the meeting for a further 30 minutes

 

195.

Warley Playing Area pdf icon PDF 103 KB

To follow.

Additional documents:

Minutes:

As part of the emerging Leisure Strategy a phased approach had been agreed for any workstreams identified as part of it.

 

One of these workstreams was to investigate opportunities at King George’s Playing Fields and Warley Playing Fields.

 

The Council currently operated 29 play areas around the Borough as part of its outdoor leisure provision, one of which is at Warley Playing Fields.

 

As part of the work around Warley Playing Fields it had been identified that the play area was in need of refurbishment following the removal of a number of items of equipment.

 

In addition to this it had been identified that there is an opportunity to establish a new outdoor gym in the Borough as part of the ongoing improvements to Warley Playing Fields.

 

Mr Anderson informed the Members that the workgroup has been looking at number of workstreams, one of these is the play area at Warley Playing Fields, which hasn’t been refurbished for approx. 20 years. Over the past 12 months some damage and outdated equipment has been removed.

 

Section 106 funds has been made available for the refurbishment of the play area, as part of the scheme, we also have looked at establishing the Council’s first Outdoor Gym, in conjunction with Health and Wellbeing Board.

 

Cllr Hubbard, thanked Mr Anderson for all this hard work on the refurbishment of Warley Playing Fields.  She asked about the new location for the new Outdoor Gym, Mr Anderson informed her this will be relocated in the site of the I-Play area.

 

The Outdoor Gym at Warley Playing Fields is a pilot scheme. The Leisure Strategy will review the need for more Outdoor Gyms throughout the Borough.

A procurement exercise will need to be undertaken depending on the demand.

 

The Chair, would like to establish links between King Georges Playing Field and Warley Playing Fields in the future.

 

A motion was MOVED by Cllr Hossack and SECONDED by Cllr Ms Sanders to approve the recommendations in the report.

 

A vote was taken by a show of hands and it was RESOLVED UNANIMOUSLY that:

 

1.    Members to approve the capital investment [as outlined in the report] and authorise Officers to initiate a refurbishment of the existing play area at Warley Playing Fields.

 

2.    That Members delegate authority to the Chair of Community, Health and Housing together with the Officers and Members of the Leisure Strategy Working Group and the Health and Wellbeing Board to determine the final design of an outdoor gym at Warley Playing Fields.

 

3.    That once a final design is established that Officers proceed with

procuring the design and installation of the outdoor gym facility at

Warley Playing Fields.

 

Reasons for Recommendation

To allow for the refurbishment of a degraded and aged play facility at Warley Playing Fields.

 

To ensure a safe and engaging facility is provided for the expanding local community.

 

 

196.

Brentwood Community Funding Allocation pdf icon PDF 91 KB

To follow.

Additional documents:

Minutes:

 

The Brentwood Community Fund was set up to give Brentwood’s communities the opportunity to provide local initiatives to improve the quality of life for local people living in the borough. The Community Fund of £16,300 is currently allocated within an existing 2017/18 budget, and grants of up £2,000 are available for applicants. The funding was open from 3 April until 29 September 2017. A summary of the applications and the officers scoring sheet is attached in Appendix B.

 

A motion was MOVED by Cllr Hossack and SECONDED by Cllr Poppy to approve the recommendations in the report.

 

A vote was taken by a show of hands and it was RESOLVED UNANIMOUSLY:

 

1.                    That Members agree to fund those projects highlighted in green as outlined in Appendix B out of the Community Fund.

 

Reasons for Recommendation

Each application has been subject to a robust, independent and transparent scoring process to ensure fairness in the allocation of funding (Appendix C). Once received the applications were scored by a panel of officers looking at the following key priorities:

 

·      Evidence that the bid meets the criteria, the Council’s priorities and expected outcomes

·      Evidence that the community has been involved in the development and implementation of the project

·      Evidence that the bid supports the promotion of volunteering and community participation

·      Evidence that the applicant has sought additional external funding or in-kind value (such as the use of volunteers) for the project

·      Evidence that the project is sustainable once the Council’s contribution has ceased.

 

Once the applications were individually scored they were ranked by their score. The recommendations by officers of the projects that met the key priorities and the amount of funding that is recommended is attached in Appendix B of this report.

 

Those applications marked green are recommended to receive funding.

 

Notifications will be made to all those applicants that applied. Successful applicants will also have to agree to any terms stipulated within the conditions of the grant being awarded. Successful applicants will also need to complete a self-monitoring report once their project has been completed.

 

Any unsuccessful applicants to the Community Fund will be offered the following support: Face to face meeting with the Partnership, Leisure and Funding Manager to review their prospective application; offered a funding training session via Brentwood Council for Voluntary Services which includes tips on submitting a good funding application. Members will also be encouraged to assist in this process; Organisations will also be signposted to the Open 4 Community on the Council’s website to look at other sources of external funding to support their project if applicable.

 

 

197.

Community Event Programme 2018/2019 pdf icon PDF 96 KB

Additional documents:

Minutes:

Currently the Council’s organises Family Fun Days, Strawberry Fair,

Lighting Up Brentwood and Shenfield Christmas Fayre. The planned events programme for 2018/19 is before Members today in Appendix A, which will be subject to Members agreement and also subject to the annual budget setting process.

 

The Chair, expressed concerns about the financial cost of the events, especially relating to the income gap relating to Lighting up Brentwood and

Shenfield Christmas Fayre.

 

Shenfield Christmas Fayre Event this year, was on some date as the Billericay Christmas Event, would this event be more successful if on an alternative date.

 

Cllr Cloke, Ingatestone were unable to have their Christmas Fayre this year, due to funding.  He requested that financial support be made available for all Wards wishing to have a Christmas Event in the Borough.

 

Cllr Wiles, request clarification on the figures in Appendix A and asked Mrs Anderson, to confirm that Lighting up Brentwood is likely to be in deficit and that the other events are due to make a profit, subject to sponsorship and stallhollder income. This was confirmed by the Officer, who clarified that all events are covered under Event Cancellation insurance, but also by the amount of stallholder and sponsorship income received. There is an allocated budget to hold these events, but there are additional costs implications for the events such as overtime, depot services which also contribute to the overall costs of the events.

 

The Chair, requested a review of cost for events going forward and which maybe could be included in the Leisure Strategy.  Views on sponsorship and the option of outside provider were also discussed.

 

A motion was MOVED by Cllr Hossack and SECONDED by Cllr Poppy to approve the recommendations in the report.

 

A vote was taken by a show of hands and it was RESOLVED that:

 

1.    That Members agree to the Event Plan for 2018/19 as set out in

Appendix A, subject to the annual budget setting process.

 

Reasons for Recommendation

The Community events programme provides a platform for all service areas across the Council to promote new initiatives, projects or as a means of consultation with the public. The Council will work with the local business clusters, community groups and voluntary sector organisations to develop the community events so that will enhance and support the support the local community.

 

198.

Termination of Meeting

Additional documents:

Minutes:

At 10.00pm in accordance with Rule 10.1 of the Council’s procedural rules, Members resolved to continue the meeting for a further 30 minutes

199.

Urgent Business pdf icon PDF 95 KB

Additional documents:

Minutes:

Disabled Access Improvements – King George’s Playing Fields Bowls Facility

 

King George’s Playing Fields is home to two of the Council’s three public amenity lawn bowls greens and the two resident clubs of Brentwood Bowls Club and Central Essex Bowls Club respectively.

 

Due to the age of the greens and a lack of investment over the last decade the infrastructure, in particular access arrangements is limited and not suited to a modern club wanting to attract new Members from all walks of life including and especially those with limited physical mobility.

 

The report before Members is requesting an agreement in principle to apply to both the Health and Wellbeing Board and also the Disabled Facilities Grant to jointly fund access improvements to the public bowling greens in the form of new DDA compliant ramps and steps leading to the lower of the two public greens.

 

A motion was MOVED by Cllr Hossack and SECONDED by Cllr Poppy to approve the recommendations in the report.

 

Mr Carter, looking into using the Better Care Fund to assist this project, and would seek support from the Health and Wellbeing Board to approve funding.

 

A vote was taken by a show of hands and it was RESOLVED UNANIMOUSLY that:

 

 

1.            Members to agree in principle to a project to construct new DDA compliant access ramps and steps to the lower public bowls green at King George’s Playing Fields.

 

2.            Members agree to Officers applying to the Health and Wellbeing Board and also the Disabled Facilities to use the Better Cars Fund monies to fund the project.

 

 

3.         Members delegate authority to Officers to engage with both Brentwood Bowls Club and Central Essex Bowls Club to progress a final design for the access point and then if successful in obtaining funding to proceed and complete works before the start of the 2018 playing season.

 

 

Reasons for Recommendation

To allow Officers to progress applications to the Health and Wellbeing Board and also the Better Care Fund scheme for funding to improve the ramped access to the bowls facility at King George’s Playing Fields.

 

To allow for the degraded and now unusable disabled access to the lower green at King George’s Playing Fields bowls facility to be rebuilt in line with DDA requirements to improve and enhance access to the facility.

 

To ensure that works can be completed before the commencement of the 2018 playing season.

 

 

 

The meeting concluded at 10:05pm